When you install enclosures into a Network Equipment-Building
System (NEBS) compliant installation, each enclosure must have a reliable
electrical earth connection that is separate to any earth connections
provided by power supply cables.
On
system enclosures, this connection is made by using the front enclosure
mounting screws that are part of the standard installation described
in
Installing the support rails and
Installing a Storwize V7000 Gen2 for Lenovo and Storwize V7000 Gen2+Lenovo Storage V series control enclosure. To provide a reliable electrical earth connection, the
upright mounting rails of the racks into which enclosures are installed
must meet the following requirements before installing the support
rails and enclosures:
- Upright mounting rails must not be painted, oxidized or otherwise
insulated from the enclosure flanges and mounting rails. If paint,
oxidization or other insulation is present, it must be removed and
the metal must be brought to a bright, non-corroding finish.
- Upright mounting rails must have their own NEBS-compliant connection
to earth, independent of the earth connections provided by any power
supply cables.
Notes:
- If the
system is required to be NEBS-compliant, some system configuration
settings must be made. For details, see Configuring a system to be NEBS-compliant.
- For more information about
configuration guidelines and restrictions, see the following website: https://datacentersupport.lenovo.com
- If a Lenovo Storage V series system is clustered with a Lenovo Storage V series system,
NEBS compliance cannot be enabled. NEBS compliance is not supported
on Lenovo Storage V series systems.