To power up a 2U expansion enclosure, install the power
cords and check the status LEDs on installed canisters.
Use either the rack PDU power cords that are supplied with
the expansion enclosure, or the country-specific power cords bought
as an option. Two cords are required.
To power on the system, complete the following steps.
- Power on all 2U expansion
enclosures by connecting both power supply units of the enclosure
to their power sources, by using the supplied power cables.
If the power sources have circuit breakers or switches, ensure
that they are turned on. The enclosure does not have power switches.
Repeat this step for each expansion enclosure in the system.
Note: Each enclosure has two power supply
units. To provide power failure redundancy, connect the two power
cords to separate power circuits.
- Check the light-emitting
diodes (LEDs) on each 2U expansion canister (see Figure 1).
Figure 1. LEDS on 2U expansion canisters
- Wait for all 2U expansion
canisters to finish powering on.
- Power on the control enclosure by connecting both power
supply units of the enclosure to their power sources, by using the
supplied power cables.
If the power sources have circuit breakers or switches, ensure
that they are turned on. The enclosure does not have power switches.
Note: Each enclosure has two power supply
units. To provide power failure redundancy, connect the two power
cords to separate power circuits.
- Check the LEDs on each node canister in the control enclosure
(see Figure 2).
Figure 2. Node canister LEDs