The recover system procedure recovers the
entire storage system if the system state is lost from all control
enclosure node canisters.The procedure
re-creates the storage system by using saved configuration data.The saved configuration data is
in the active quorum disk and the latest XML configuration backup
file. The recovery might not be able to restore all volume data.
This procedure is also known as Tier 3 (T3) recovery.
CAUTION:
If the system encounters a state where:
- No nodes are active, and
- One or more nodes have node errors that require
a node rescue, node canister replacement, or node firmware reinstallation
STOP and contact IBM Remote Technical
Support. Initiating this T3 recover system procedure while in this
specific state can result in loss of the XML backup of the block volume
storage configuration.
Attention:
- Run service actions only when directed by the fix procedures.
If used inappropriately, service actions can cause loss of access
to data or even data loss. Before you attempt to recover a storage system,
investigate the cause of the failure and attempt to resolve those
issues by using other fix procedures. Read and understand all
of the instructions before you complete any action.
- The recovery procedure can take several hours if the system uses
large-capacity devices as quorum devices.
Do not attempt the recover system procedure
unless the following conditions are met:
- All of the conditions have been met in When to run the recover system procedure.
- All hardware errors are fixed. See Fix hardware errors
- All node canisters have candidate status. Otherwise,
see step 1.
- All node canisters must be at the same level
of code that the storage system had before the system failure. If any node canisters were modified or replaced,
use the service assistant to verify the levels of code, and where
necessary, to reinstall the level of code so that it matches the level
that is running on the other node canisters in the system.
The system recovery procedure is one of several tasks
that must be completed. The following list is an overview of the tasks
and the order in which they must be completed:
- Preparing for system recovery
- Review the information regarding when to run the recover system
procedure.
- Fix your hardware errors and make sure that all nodes in the system
are shown in service assistant or in the output from sainfo
lsservicenodes.
- Remove the system information for node canisters
with error code 550 or error code 578 by using the service assistant,
but only if the recommended user response for these node errors has
already been followed. See Removing system information for node canisters with error code 550 or error code 578 using the service assistant.
- For Virtual Volumes (VVols), shut down the services for any instances
of Spectrum Control Base that are connecting to the system. Use the
Spectrum Control Base command service ibm_spectrum_control
stop.
- Running the system recovery. After you prepared the system for
recovery and met all the pre-conditions, run the system recovery.
Note: Run the procedure on one system in a fabric at
a time. Do not run the procedure on different node canisters in the
same system. This restriction also applies to remote systems.
- Completing actions to get your environment operational.
- Recovering from offline volumes by using the CLI.
- Checking your system, for example, to ensure that all mapped volumes
can access the host.